Data Model

Effort Points and Time Estimation

Turn effort points on per item type and choose the point format, and define the three-point time-estimate ranges (optimistic, likely, pessimistic) each item type offers.

DevStride supports two kinds of estimate, configured on two Settings pages and both assigned per item type:

  • Effort points — a relative size (story points). Good for velocity and sprint planning.
  • Time estimates — hours, entered as an optimistic / likely / pessimistic range and combined with the PERT formula into an estimate with a confidence interval. Good for forecasting and capacity.

You can use either, both or neither; each item type decides.

Effort Point Estimation

Configure Settings → Data Model → Effort Point Estimation (needs Manage work types). The page lists every item type with an Effort Points setting:

OptionWhat people can enter
DecimalAny number, including fractions (2.5).
IntegerWhole numbers only.
Fixed ListOnly the values you list, comma-separated, for example 1, 2, 3, 5, 8, 13 for Fibonacci or 1, 2, 4, 8 for powers of two.
DisabledThe type is not pointed; the Point Estimate field does not appear on its items.

Changes save as you make them. Point a type that represents the unit of planning (Stories, Tasks); leave container types (Epics, Features) disabled and let their totals roll up.

People set an item's points from the Point Estimate field in the item drawer sidebar, the Points cell of a table, or the bulk-edit menu. See Point estimates.

Time Estimation

Configure Settings → Data Model → Time Estimation (needs Manage work types). Here you define named estimation ranges — T-shirt sizes, typically — so people pick a size and get sensible hours they can then refine.

1 - Create Range

Click New and enter a Range Name plus its Default Hours: Optimistic, Likely and Pessimistic. A new organization starts with XXXS (0.25 / 0.5 / 1 hrs) through XXXL. People can refine the three numbers on an individual item; the range just gives them a starting point.

2 - Group into Collections

Click New to create an Estimation Collection, choose its Confidence Percentage (68, 95 or 99, that is one, two or three standard deviations), and drag ranges into it. The confidence level decides how wide the ± margin on the computed estimate is. The starter collection is Story Sizes.

3 - Assign to Item Types

For each item type choose a collection, or Time Estimates Disabled to hide time estimates on that type.

Optimistic and pessimistic are optional

If your teams only ever estimate the likely hours, turn on Optimistic and pessimistic are optional at the top of the Time Estimation page. Changing it needs permission to manage the organization's settings, and it applies to the whole organization.

With it on, the estimate dialog marks Optimistic and Pessimistic (optional). Type only Likely and save: the blank bounds take the likely value, so the estimate is exactly the likely figure with no ± range. If you do type a bound, it is kept and still checked (optimistic can't exceed likely, likely can't exceed pessimistic). Reopening a likely-only estimate shows its bounds blank again, so changing Likely carries them along.

It's off by default. Turned off, every estimate needs all three values, as before.

How people estimate an item

In the item drawer, click Time Estimate, pick a range or type the optimistic, likely and pessimistic hours (only likely when optimistic and pessimistic are optional), and review the Range, Estimate and Confidence before Save Estimate. The estimate is the PERT weighted mean, (optimistic + 4 × likely + pessimistic) ÷ 6, shown with a ± margin at the collection's confidence level. Time estimates also appear in the Time Estimate cell of tables and in the bulk-edit menu. See Time estimates and best practices.