Link Mode keeps a dependency chain consistent when a date slips. With it on, moving an item's due date moves every item that depends on it by the same number of days, and the shift carries on down the chain. With it off, you move one bar and decide the rest yourself.
There are two switches. The organization-wide Enable Link Mode setting (on by default) governs date changes made anywhere in DevStride and through the API. The Linked / Unlinked toggle on a Gantt chart overrides it for changes made on that chart.
Say the API epic is due 10 June and the mobile epic, which depends on it, runs 11 to 25 June. You drag the API epic's due date to 17 June, a 7-day slip.
Details that matter:
| You change a due date in | Cascade is decided by |
|---|---|
| A Gantt chart (drag, resize, table cell, Shift + click) | The chart's Linked / Unlinked toggle. The organization setting is ignored here. |
| The item workspace, Items Table, Map or a board | The organization's Enable Link Mode setting |
| The API or the DevStride MCP server | The request's own staticMode value if provided, otherwise the organization setting |
So with the organization setting on, a due date edited in the Items Table cascades just like a Gantt drag in Linked mode. With it off, only Gantt charts in Linked mode cascade.
The link / unlink button in the chart's control strip switches modes; Shift + M does the same.
Your choice is remembered in your browser across charts and is stored in saved views, so a view can open a chart in the mode its audience expects. Scenario recordings note which mode each move used. See Navigating the timeline.
Outside the Gantt, with the organization setting off, DevStride does not move dependents but it does check. If a new start or due date conflicts with a related item's dates, a Relationships Date Warning dialog explains the conflict and asks you to Confirm or Cancel. Turning the setting on replaces the warning with the automatic shift.
On a Gantt in Unlinked mode, the bar you move is the only one that moves. Dependency lines stay drawn, so an overlap shows up as a line pointing backwards.
Admins change the default in Configure Settings → Admin → Global Automations: tick or untick Enable Link Mode (Allow item actions to propagate down the dependency chain). It saves immediately. The same page holds Sync work item dates with their cycles and Automate New/Done, which are separate settings. See Global Automations.
Before a large move, open the Dependency Graph to see how far the cascade will reach, or rehearse it in a scenario.
Tips for Effective Gantt Chart Planning
Habits that keep a DevStride Gantt chart truthful and useful: date at the right level, keep dependency chains clean, use Linked mode on purpose, rehearse with scenarios, and give each audience a saved view instead of a new chart.
Setting Up Your Kanban Board
How a Kanban board maps onto DevStride — statuses, status collections, WIP limits and a perpetual board — and where each piece is configured.