Gantt Charts

Gantt Charts Toolbar

Reference for every control on a Gantt chart: the chart picker and filter bar, the control strip with zoom, row height, scenarios, Linked mode, snap to cycles, progress, level buttons and scrolling, the Options panel, and keyboard shortcuts.

The controls on a Gantt chart sit in three places: the top-right actions (create and import), the filter bar (chart picker, filters, views, options), and the control strip above the timeline. This page lists them all. For when to reach for each, follow the links into the how-to pages.

Top-right actions

ControlWhat it does
+ CreateMenu with Gantt Group, Gantt Chart, Initiative and Milestone. Entries you lack permission for are greyed out with the key named in a tooltip.
ImportOpens Add to initiative to bring existing workstreams and items onto the selected chart. Disabled until the chart has an initiative.

See Add to Gantt.

Filter bar

ControlWhat it does
Gantt dropdownLists every chart, grouped by Gantt group with ungrouped charts under Other. Search narrows it.
FiltersNarrows the workstreams and items shown. Filters: Assignee, Persona, Team, Board, Cycle, Status, Item Type, Priority, Tag, Field, Parent, Start Date, Due Date, Completion Date, Time Spent, Creator, Watchers, Include Archived, and Advanced Filters. Initiatives and milestones always show.
ViewsSaved views: Save as view, and a searchable list with Copy link, Edit view and Delete view. A view stores the chart, filters, zoom and row height, expanded rows, progress attribute and whether progress counts the lowest-level work, Linked/Unlinked mode, item-number visibility, the table's columns and widths, scroll position and any applied baseline scenario.
OptionsToggles: Hide Bounding Boxes, Hide Inline Labels, Hide Relationships, Show Item Numbers, Sort by Start Date, remembered in your browser; Show Bar Progress By and Progress from Lowest-Level Work (see Show bar progress by); and Table columns, which opens the Manage Columns picker to show, hide and reorder the table's columns (see Choose columns). Hidden columns show as a pill such as 2 hidden columns.

Above the table, next to the chart name: Edit gantt details (pencil) and Delete this gantt, shown when you can manage the chart. An active scenario badge appears there too.

Control strip

From left to right.

Scenarios

Scenarios opens the scenario dialog: start a New scenario, or pick an existing one to view as a baseline, record into, rename or delete. While recording, the button pulses and gains Cancel and discard scenario and Save scenario beside it; clicking it then shows the recorded changes. Disabled while filters are applied, while remote updates are in flight, or when you cannot edit the chart. See Scenario Planning.

Horizontal zoom

The Horizontal zoom slider steps through ten presets from years to days. The button beside it shows the current scale in pixels per day; click it to pick a preset by name.

Scale (px/day)Header
0.25, 0.5, 1Years / Quarters
2, 4Quarters / Months
8, 16Months / Weeks
32, 64Weeks / Days
100Days

New charts open at 4 px/day. Double-click an empty part of the timeline to zoom in a step; Shift + double-click zooms out. Zoom is remembered per chart and stored in saved views.

Row height

The Row height slider and the field beside it set the height of every row in pixels: 20 to 50, default 35. Type a value and press Enter; out-of-range values flash and are clamped.

Linked / Unlinked mode

The link / unlink button sets whether due-date changes made on this chart cascade to dependent items.

  • Linked mode: Item actions will propagate down the dependency chain.
  • Unlinked mode: Item actions will not propagate to its dependency chain.

Shift + M toggles it. Remembered in your browser and in saved views. Full behavior in Link Mode.

Snap to cycles

The magnet opens Select board folder. Pick a folder to overlay its cycles as bands behind the bars; the button takes the cadence's color while a folder is selected, and the tooltip names the folder and cadence. With a folder selected, moving a work item's bar is confined to one cycle and assigns the item to that cycle's board. Clear the folder from the same dialog. Not stored in saved views. See Navigating the timeline.

Show bar progress by

Options → Show Bar Progress By offers Items completed, Point estimate (if any item type uses points), Time estimate (if any uses time estimates) and Hide progress. It sets both the bar fill and the Progress column; Hide progress removes the column. (It used to be a separate button on the control strip.)

Below it, Progress from Lowest-Level Work changes what is counted. Off (the default), an item's progress comes from its direct children. On, it comes from its lowest-level work: every item beneath it, at any depth, that has nothing under it. A module with 10 epics and 100 stories, 90 of them done, shows 0% counted from direct children while no epic is finished, and 90% counted from the lowest-level work. An epic with no stories yet counts as one unfinished piece. It works for items, points and time, a manual percentage still wins, and the choice is saved with the view.

Collapse and expand by level

Two buttons collapse or expand the whole chart one hierarchy level at a time. Their tooltips say exactly what the click will do, for example Expand 3 workstreams at level 2, and they disable when there is nothing left to expand or collapse. Shift + - and Shift + = do the same from the keyboard.

Scrolling

ControlWhat it does
Scroll gantt to the left / right (chevrons)Hold to scroll continuously
Go to today (calendar)Centers the view on the TODAY line

You can also drag an empty part of the timeline to pan, and click a date in the header to center on it.

Table controls

ControlWhat it does
Divider between table and timelineDrag to resize sidebar
Chevron on the dividerClick to collapse the table; Click to expand brings it back
Column header edgesResize columns: drag an edge, hold Shift to resize all, double-click to reset
Right-click a row, or Options (vertical dots) on itRow menu. Workstream and item rows get the Items Table's menu (Open, Edit, Copy, Duplicate, Archive, Delete and more), acting on the ticked rows when the clicked row is ticked, plus Expand children, Collapse children, Create new and Remove from gantt for a single row. Initiatives, milestones and locked rows get Edit, Expand children, Collapse children, Add existing workstreams or items, Create new and Delete (by row type and permission)
Row checkboxTick up to 25 rows; Shift + click ticks a range, the header checkbox ticks every row showing
Row grab handleDrag to reorder rows or move a first-level row to another initiative; or focus it and use Space and ↑ / ↓

Details in Navigating the table.

Shift + click to auto-set dates

In the Start date and Due date cells, and on a workstream bar's handles, Shift + click sets the date from the work beneath:

  • Start date snaps to the earliest descendant start.
  • Due date snaps to the furthest descendant due date.
  • A Date missing cell snaps to the inferred date.

Keyboard shortcuts

ShortcutAction
Shift + MToggle Linked / Unlinked mode
Shift + - / Shift + =Collapse the deepest open level / expand every collapsed initiative and workstream showing
- / + or =Collapse / expand the row whose Name cell is focused
Arrow keysMove between table cells
Cmd/Ctrl + ↑ / ↓Jump to the previous / next sibling row
Enter, or start typingEdit the focused cell
EscCancel the edit
Double-click empty timelineZoom in
Shift + double-clickZoom out
Shift + click a date cell or bar handleAuto-set the date from descendants

In the Scenarios dialog: N focuses the new-scenario field, R records into the focused scenario, E renames it, Delete deletes it.