Gantt Charts

Add to Gantt

Every way to put work on a Gantt chart: initiatives, milestones, importing existing workstreams and items, creating new work from a row, and the Gantt bulk action from the Items Table or Map.

A chart shows work that already exists in DevStride. You add structure (initiatives, milestones) on the chart itself and then point the chart at workstreams and items. Nothing is copied: the bar you see is the item's own dates, and removing something from the chart leaves the item alone.

You need edit rights on the chart (MANAGE_OWN_GANTTS for your charts, MANAGE_ALL_GANTTS for others'). Creating new items from the chart also needs CREATE_ITEMS_AND_WORKSTREAMS.

Add an initiative

Initiatives are the lanes of the chart. Every imported workstream or item sits under one.

  1. Click + Create in the top-right and choose Initiative (on an empty chart, + New initiative does the same).
  2. In New Initiative, enter a Name (at least 3 characters), an optional Description, and pick a Color. The color paints the initiative's bounding box on the timeline.
  3. Confirm.

Initiatives have no dates of their own; their bar stretches from the earliest to the latest date of the work inside. Edit one by double-clicking its row or via Options then Edit. Options then Delete removes the initiative and its rows from the chart without deleting any items.

Add a milestone

A milestone is a single date drawn as a diamond. Use it for anything that is a point rather than a span: a release, a contract date, a demo.

  1. Click + Create and choose Milestone.
  2. In New Milestone, enter a Name, optional Description, a Color, and the Date.
  3. Confirm.

Milestones sit at the top level alongside initiatives and can be dragged on the timeline. They can be the source or target of a Dependency or Related line, so "launch depends on these three epics" is one chart gesture. Edit by double-clicking; delete via Options then Delete.

Import existing workstreams and items

  1. Click Import in the top-right. It is enabled once the chart has at least one initiative; the tooltip explains if it is not.
  2. In Add to initiative, choose the Initiative.
  3. Click Items / Workstreams and pick from the workstream map. Select whole workstreams (their children come along and load when you expand) or single items, from any level and any board. Things already on the chart are disabled.
  4. Click Add Items.

From an initiative row, Options then Add existing workstreams or items opens the same dialog with that initiative preselected.

Create new work from the chart

On an initiative or workstream row, Options then Create new offers Work item and, for initiatives and workstreams, Workstream. The quick-add dialog creates a real item in that location and places it on the chart in one step. New items without dates appear with Date missing and an inferred bar you can accept with one click.

From the Items Table or the Map

When you are already looking at the work, bring it to a chart from there:

  1. Select the items in the Items Table or the Map.
  2. Open the bulk action menu and choose Gantt.
  3. In Add to Gantt, pick the Gantt, then an Initiative. Initiatives that already contain all the selected items are disabled; Create one lets you add a new initiative by name without leaving the dialog.
  4. Confirm.

The Gantt action only appears if you hold MANAGE_OWN_GANTTS or MANAGE_ALL_GANTTS.

Remove work from a chart

On a first-level row (directly under an initiative), Options then Remove from gantt, then Remove in the confirmation. The item keeps its dates, relationships and everything else; only this chart forgets it. Children of an imported workstream cannot be removed individually; remove the workstream or move the child in the workstream itself.

What appears on the timeline

The item hasYou see
Start and due datesA bar in place
Only one of the twoA bar using the known date and an inferred one; the missing cell reads Date missing
No datesAn inferred placeholder bar; click it once, or Shift + click the cell, to accept the dates
A cycle board, with Sync work item dates with their cycles onThe cycle's dates

Next: Gantt Charts Toolbar for the controls, or Navigating the timeline to start moving bars.