Once a chart exists (see Setting Up Gantt Charts), most of your time on it is spent reading, not editing. This page covers how to get the chart to show exactly the slice you need.
The Gantt picker sits at the left of the filter bar. Click it to see every chart you can open, grouped by Gantt group with ungrouped charts under Other, and type in Search to narrow the list. The chart name and description also appear above the table, with Edit gantt details and Delete this gantt if you can manage the chart.
The search at the top of the screen can jump straight to a chart too: type the chart's name, or type #roadmap to list the Gantts you opened recently. See Search & Recent Places.
The page address always names the chart you have open, and the saved view applied to it, the same way a board's address names its board. Copy the address from your browser to send someone straight to that chart; they need access to it to open it. Opening a chart link, or picking another chart in the Gantt picker, while a Gantt is already open switches to that chart, and your browser's Back button returns to the chart (and view) you had before; Forward goes to the chart you switched to.
| You see | It means |
|---|---|
| A thin colored box spanning several rows | An initiative. Its box covers everything inside it; the color is the initiative's color. Hide Bounding Boxes in Options turns these off. |
| A solid bar | A workstream or item with a start and due date. Workstream bars show the title and completion, for example Checkout (40%), until they reach 100%. |
| A diamond | A milestone: a single date, no duration. |
| A partly filled bar | Progress. What fills the bar is set by Options → Show Bar Progress By (items completed, point estimate, time estimate, or hidden), counted from direct children or, with Progress from Lowest-Level Work on, from every item at the bottom of the tree. |
| Red row title | The item is overdue: its due date has passed and it is not done. A calendar icon with a tooltip shows the due date. |
| Date missing in a date cell | The item has no start or due date. A placeholder bar is drawn at an inferred position; click the bar once, or Shift + click the cell, to accept the inferred dates. |
| Lock icon and Restricted in Cycle / Board | The item is on a board you cannot view. |
| Archive icon | The item is archived. Archived items only appear when Include Archived is on. |
| Import icon | The item was brought in by an import or integration. |
| Orange solid line between bars | A Dependency: the arrow points from the blocker's end to the dependent's start. |
| Green dashed line | A Related link with no scheduling meaning. |
| TODAY line | Today's date. Charts open scrolled to it. |
Hover a bar to highlight its row in the table and its dependency lines. Items whose bar is off-screen get a small arrow button at the chart edge labeled with the item name; click it to scroll there.
The chart loads with initiatives expanded and workstreams collapsed, so a leadership view is one click away and the detail is one click further. Visual indicators roll up: a workstream shows the combined progress of its children, and an overdue child turns its own row red so you can spot trouble before expanding.



Click Filters in the filter bar. A chart often holds several teams' work; a filter shows one slice without changing the chart for anyone else.
| Filter | Narrows to |
|---|---|
| Assignee, Persona | Who the items are assigned to (Persona appears when personas are enabled) |
| Team | Items on the selected teams' boards |
| Board, Cycle | Items on specific boards, or within a range of cycles |
| Status | Workflow status |
| Item Type | Your item types |
| Priority, Tag, Field | Priority, tags, and custom field values |
| Parent | Items under a chosen parent |
| Start Date, Due Date, Completion Date | Date ranges |
| Time Spent | Logged time thresholds |
| Creator, Watchers | Who created or watches the item |
| Include Archived | Also show archived items |
| Advanced Filters | Build a query combining fields |

Initiatives and milestones always stay; filters apply to the workstreams and items beneath them. Clear a single filter by clicking its pill and deselecting values, or remove them all with the x on the filter bar.

Snap to cycles (magnet) overlays one board folder's cycles as bands behind the bars. It is a lens, not a filter: the bars do not change, but you can see which sprint or program increment each piece of work lands in.
In the example, the chart is filtered to the GTM team's activities (1), but the bands still show the WebDev team's sprints (2). That is useful on purpose: GTM can see which engineering sprint their work depends on.

To switch lenses, click the magnet, expand to a different folder (here the GTM program increment folder) and click Select.


Clear the lens with the clear control in the same dialog. While a lens is on, dragging a work item is constrained to a single cycle and re-assigns its board; see Navigating the timeline.
Options in the filter bar holds five view toggles and the Table columns button. The toggles are remembered in your browser for every chart.
| Toggle | Effect |
|---|---|
| Hide Bounding Boxes | Removes the initiative and parent boxes around grouped bars |
| Hide Inline Labels | Removes the text drawn on bars |
| Hide Relationships | Removes dependency and related lines |
| Show Item Numbers | Shows each item's number before its title in the Name column |
| Sort by Start Date | Lists rows earliest first at every level instead of in their saved order. A row sorts by its own start date or the earliest start under it, else its due date; rows with no dates come last. This changes only the view: the saved order is untouched, and rows cannot be dragged into a new order while it is on (bars can still be moved). A filter-bar chip, Sorted by start date, shows it is on and clears it. |
Table columns opens the Manage Columns picker, the same one the Items Table uses: show, hide and reorder the table's columns, including Items Table columns such as Assignee, Status, Priority, Tags, Team and your custom fields, which start hidden. See Choose columns.
A saved view captures the whole state of the chart so stakeholders open the same picture every time. Here is a view that shows only critical-priority work.




To use or share a view, click Views, find it with Find, and use the row actions: Copy link, Edit view, Delete view. Opening a shared link switches to the right chart and applies everything the view stored.

Saving views needs CREATE_STORED_VIEW. The snap-to-cycles folder is not part of a view.
Double-click any row, or choose Options then Edit, to open the item workspace for a workstream or item, or the edit dialog for an initiative or milestone. Open in new tab keeps the chart where it is. See Navigating the table for inline editing.
Perpetual board items have no cycle to borrow dates from. Give them a start and due date in the item, in the Items Table, or by accepting the inferred date on the chart. If they really should be scheduled, consider moving them to a cycle board. See Setting up and using perpetual boards.
Cycle dates: items inherit their cycle's dates only when the organization setting Sync work item dates with their cycles is on.
Dependencies: a bad chain moves good dates. Check the Dependency Graph before you enable Linked mode on a chart you did not build.
Granularity: keep executive charts at workstream level and let people expand. Groups, filters and saved views are cheaper than more charts.
Track Progress: Setting Up Gantt Charts
Create a Gantt chart in Track Progress, add initiatives and milestones, import the workstreams and items you want to track, and get dates onto the timeline.
Using Gantt Charts: Navigating the timeline
Move and resize bars, zoom and pan, snap work to a team's cycles, draw dependencies between bars, and choose whether a slipped date pushes dependent work.