Track Progress: Gantts

Viewing Gantt Charts

Pick a chart, read the bars and rollups, expand to the level you need, filter to one team, look through another team's cadence, and save the result as a shareable view.

Once a chart exists (see Setting Up Gantt Charts), most of your time on it is spent reading, not editing. This page covers how to get the chart to show exactly the slice you need.

Pick a chart

The Gantt picker sits at the left of the filter bar. Click it to see every chart you can open, grouped by Gantt group with ungrouped charts under Other, and type in Search to narrow the list. The chart name and description also appear above the table, with Edit gantt details and Delete this gantt if you can manage the chart.

The search at the top of the screen can jump straight to a chart too: type the chart's name, or type #roadmap to list the Gantts you opened recently. See Search & Recent Places.

The page address always names the chart you have open, and the saved view applied to it, the same way a board's address names its board. Copy the address from your browser to send someone straight to that chart; they need access to it to open it. Opening a chart link, or picking another chart in the Gantt picker, while a Gantt is already open switches to that chart, and your browser's Back button returns to the chart (and view) you had before; Forward goes to the chart you switched to.

Read the chart

You seeIt means
A thin colored box spanning several rowsAn initiative. Its box covers everything inside it; the color is the initiative's color. Hide Bounding Boxes in Options turns these off.
A solid barA workstream or item with a start and due date. Workstream bars show the title and completion, for example Checkout (40%), until they reach 100%.
A diamondA milestone: a single date, no duration.
A partly filled barProgress. What fills the bar is set by Options → Show Bar Progress By (items completed, point estimate, time estimate, or hidden), counted from direct children or, with Progress from Lowest-Level Work on, from every item at the bottom of the tree.
Red row titleThe item is overdue: its due date has passed and it is not done. A calendar icon with a tooltip shows the due date.
Date missing in a date cellThe item has no start or due date. A placeholder bar is drawn at an inferred position; click the bar once, or Shift + click the cell, to accept the inferred dates.
Lock icon and Restricted in Cycle / BoardThe item is on a board you cannot view.
Archive iconThe item is archived. Archived items only appear when Include Archived is on.
Import iconThe item was brought in by an import or integration.
Orange solid line between barsA Dependency: the arrow points from the blocker's end to the dependent's start.
Green dashed lineA Related link with no scheduling meaning.
TODAY lineToday's date. Charts open scrolled to it.

Hover a bar to highlight its row in the table and its dependency lines. Items whose bar is off-screen get a small arrow button at the chart edge labeled with the item name; click it to scroll there.

Summary and detail levels

The chart loads with initiatives expanded and workstreams collapsed, so a leadership view is one click away and the detail is one click further. Visual indicators roll up: a workstream shows the combined progress of its children, and an overdue child turns its own row red so you can spot trouble before expanding.

  • Click the caret at the left of a row to expand or collapse that row. Children load on demand; the row shows Loading... briefly.
  • The two level buttons in the control bar expand or collapse the whole chart one level at a time. Their tooltips tell you exactly what will happen, for example Expand 3 workstreams at level 2. Shift + = expands a level, Shift + - collapses one.
  • With a row's Name cell focused, + or = expands it and - collapses it.
  • Options on a row, or a right-click, offers Expand children and Collapse children.

Filter to the work you care about

Click Filters in the filter bar. A chart often holds several teams' work; a filter shows one slice without changing the chart for anyone else.

FilterNarrows to
Assignee, PersonaWho the items are assigned to (Persona appears when personas are enabled)
TeamItems on the selected teams' boards
Board, CycleItems on specific boards, or within a range of cycles
StatusWorkflow status
Item TypeYour item types
Priority, Tag, FieldPriority, tags, and custom field values
ParentItems under a chosen parent
Start Date, Due Date, Completion DateDate ranges
Time SpentLogged time thresholds
Creator, WatchersWho created or watches the item
Include ArchivedAlso show archived items
Advanced FiltersBuild a query combining fields

Initiatives and milestones always stay; filters apply to the workstreams and items beneath them. Clear a single filter by clicking its pill and deselecting values, or remove them all with the x on the filter bar.

Look through any team's cadence

Snap to cycles (magnet) overlays one board folder's cycles as bands behind the bars. It is a lens, not a filter: the bars do not change, but you can see which sprint or program increment each piece of work lands in.

In the example, the chart is filtered to the GTM team's activities (1), but the bands still show the WebDev team's sprints (2). That is useful on purpose: GTM can see which engineering sprint their work depends on.

To switch lenses, click the magnet, expand to a different folder (here the GTM program increment folder) and click Select.

Clear the lens with the clear control in the same dialog. While a lens is on, dragging a work item is constrained to a single cycle and re-assigns its board; see Navigating the timeline.

Options panel

Options in the filter bar holds five view toggles and the Table columns button. The toggles are remembered in your browser for every chart.

ToggleEffect
Hide Bounding BoxesRemoves the initiative and parent boxes around grouped bars
Hide Inline LabelsRemoves the text drawn on bars
Hide RelationshipsRemoves dependency and related lines
Show Item NumbersShows each item's number before its title in the Name column
Sort by Start DateLists rows earliest first at every level instead of in their saved order. A row sorts by its own start date or the earliest start under it, else its due date; rows with no dates come last. This changes only the view: the saved order is untouched, and rows cannot be dragged into a new order while it is on (bars can still be moved). A filter-bar chip, Sorted by start date, shows it is on and clears it.

Table columns opens the Manage Columns picker, the same one the Items Table uses: show, hide and reorder the table's columns, including Items Table columns such as Assignee, Status, Priority, Tags, Team and your custom fields, which start hidden. See Choose columns.

Save and share a view

A saved view captures the whole state of the chart so stakeholders open the same picture every time. Here is a view that shows only critical-priority work.

  1. Click Filters, choose Priority, select Critical, and apply.

  1. Expand the rows you want visible.

  1. Click Views. The Save as view button lists the customizations it detected: filters, zoom and row height, expanded rows, the chart, the progress setting, Linked/Unlinked mode, item numbers, sorting by start date, scroll position, and an applied baseline scenario.

  1. In Save view, enter a Name and optional Description, and set Visibility to Visible only to you or Visible to coworkers. Click Save.

To use or share a view, click Views, find it with Find, and use the row actions: Copy link, Edit view, Delete view. Opening a shared link switches to the right chart and applies everything the view stored.

Saving views needs CREATE_STORED_VIEW. The snap-to-cycles folder is not part of a view.

Open an item from the chart

Double-click any row, or choose Options then Edit, to open the item workspace for a workstream or item, or the edit dialog for an initiative or milestone. Open in new tab keeps the chart where it is. See Navigating the table for inline editing.